首页 | 本学科首页   官方微博 | 高级检索  
     

水电站用爆破膜代替调压井的过渡过程和工程措施
引用本文:胡沛成 倪福生. 水电站用爆破膜代替调压井的过渡过程和工程措施[J]. 河海大学常州分校学报, 1999, 13(4): 1-6
作者姓名:胡沛成 倪福生
作者单位:河海大学机电工程学院!常州213022
基金项目:水利部水利技术开发基金项目资助!(项目编号SJ9617)
摘    要:水电站用爆破膜代替调压井新技术已成功地应用于多个水电站并取得显著的经济效益,简述了爆破膜工作原理,水力过渡过程数据模拟,并介绍了干水电站应用实例。

关 键 词:爆破膜 调压井 水电站 水力过渡过程 数据模拟

Hydraulic Transients and Engineering Solutions to Water Hammer Using Safety Membranes to Replace the Surge Chamber in a Hydropower Station
Hu Peicheng Ni Fusheng. Hydraulic Transients and Engineering Solutions to Water Hammer Using Safety Membranes to Replace the Surge Chamber in a Hydropower Station[J]. Journal of Hohai University Changzhou, 1999, 13(4): 1-6
Authors:Hu Peicheng Ni Fusheng
Abstract:Safety membranes replacing a surge chamber have been successfully used in several hydropower stations and made a great deal of profits.The article discusses the working principle,numerical simulation on the hydraulic transients and applications of safety membranes in lieu of a surge chamber.
Keywords:safety membranes  surge chamber  hydraulic transients
本文献已被 CNKI 维普 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号