利用有机朗肯循环系统回收30t/h燃煤锅炉烟气余热的热经济性评估
引用本文:刘亚玲,张诚,邹益平,陈娟,刘朝. 利用有机朗肯循环系统回收30t/h燃煤锅炉烟气余热的热经济性评估[J]. 重庆大学学报(自然科学版), 2018, 41(3): 91-99. DOI: 10.11835/j.issn.1000-582X.2018.03.011
作者姓名:刘亚玲  张诚  邹益平  陈娟  刘朝
作者单位:四川省特种设备检验研究院,成都,610061重庆大学 动力工程学院,重庆,400044
摘    要:设备选择和经济性评估对有机朗肯循环系统(ORC)热力性、经济性和环境影响至关重要。文中以R123为工质,以某厂30t/h蒸发量锅炉烟气余热回收利用作为案例,对ORC系统回收利用烟气余热进行了设备及热经济性计算分析,给出了具体设备热经济计算结果,锅炉烟道中换热管束的布置形式和尺寸。结果表明,系统单位装机容量成本为23 800元/kW,单位发电成本为0.285元/kW·h,投资回收年限为5.58年,净输出功为91.5kW,发电功率为88.5kW。考虑主要设备及运行维护费用,系统总投资约合人民币345万元。

关 键 词:有机朗肯循环  工业锅炉  热经济评估  余热利用
收稿时间:2017-09-12

Thermo-economic evaluation of using organic Rankine cycle system to recover flue gas waste heat of a 30 t/h industrial boiler
LIU Yaling,ZHANG Cheng,ZOU Yiping,CHEN Juan and LIU Chao. Thermo-economic evaluation of using organic Rankine cycle system to recover flue gas waste heat of a 30 t/h industrial boiler[J]. Journal of Chongqing University(Natural Science Edition), 2018, 41(3): 91-99. DOI: 10.11835/j.issn.1000-582X.2018.03.011
Authors:LIU Yaling  ZHANG Cheng  ZOU Yiping  CHEN Juan  LIU Chao
Affiliation:Sichuan Province Special Equipment Inspection Institute, Chengdu 610061, P. R. China,College of Power Engineering, Chongqing University, Chongqing 400044, P. R. China,Sichuan Province Special Equipment Inspection Institute, Chengdu 610061, P. R. China,Sichuan Province Special Equipment Inspection Institute, Chengdu 610061, P. R. China and College of Power Engineering, Chongqing University, Chongqing 400044, P. R. China
Abstract:Equipment selection and thermo-economic evaluation have great influence on thermodynamic performance, economic feasibility and environmental impacts of ORC (organic rankine cycle) systems. Selecting R123 as working fluid, we conduct the main parameters of equipment and thermos-economic analysis for ORC electricity generation system driven by the flue gas waste heat of a real 30 t/h industrial boiler. Then heat exchanger sizes and thermos-economic results are calculated, and the operating parameters of equipment and heat exchanger layout are put forward. The results show that the unit capacity cost, electricity production cost, payback period, net power output and electricity production power are 23 800 Yuan/kW, 0.285 Yuan/(kW·h), 5.58 years, 91.5 kW and 88.5 kW, respectively. Considering the main equipment and operation maintenance cost, the system total investment is RMB 3.45 million.
Keywords:organic Rankine cycle  industrial boiler  thermo-economic evaluation  waste heat recovery