浅谈黄土隧道施工
引用本文:郭学鹏. 浅谈黄土隧道施工[J]. 科技情报开发与经济, 2011, 21(9): 203-206
作者姓名:郭学鹏
作者单位:中铁十八局集团第三工程有限公司,青海民和,810800
摘    要:在黄土隧道施工中,进洞前要做好长管棚施工和防排水工程工作,洞内施工做好围岩量测工作,并坚持"短进尺,快循环、快封闭、严格工艺、严格标准、严格管理,及时支护、及时量测、及时反馈、及时二次衬砌"的原则施工,以确保施工质量。

关 键 词:黄土隧道  隧道施工  围岩量测  初期支护  二次衬砌

Talking about the Construction of Loess Tunnel
GUO Xue-peng. Talking about the Construction of Loess Tunnel[J]. Sci-Tech Information Development & Economy, 2011, 21(9): 203-206
Authors:GUO Xue-peng
Affiliation:GUO Xue-peng
Abstract:In the construction of loess tunnel,the long-tube shed construction and the waterproof and drainage engineering should be finished well before entering the tunnel,and in the construction inside the tunnel the measurement of surrounding rock should be done correctly,and should persist in the principle of "short footage,quick circulation,quick closure,strict technology,strict standard,strict management,immediate support,immediate measurement,immediate feedback,immediate secondary lining"for gusranteeing the construction quality.
Keywords:loess tunnel  tunnel construction  measurement of surrounding rock  primary support  secondary lining