The scheme optimization on construction diversion with discharge control feature of upstream operational reservoir
Authors:Liu Quan  Hu Zhigen  Fan Wuyi  Ni Jinchu and Li Qinjun
Institution:State Key Laboratory of Water Resources & Hydropower Engineering Science, Wuhan University, Wuhan 430072, China;State Key Laboratory of Water Resources & Hydropower Engineering Science, Wuhan University, Wuhan 430072, China;Changjiang Institute of Survey, Planning, Design and Research, Wuhan 430010, China;Changjiang Institute of Survey, Planning, Design and Research, Wuhan 430010, China;Changjiang Institute of Survey, Planning, Design and Research, Wuhan 430010, China
Abstract:There is a discharge control feature of construction diversion system with the upstream operational reservoir. The risk evaluation model of construction diversion is established by taking into consideration the risk factors of construction diversion system with discharge control feature as well as their composition. And the risk factors include the upstream operational reservoir discharge control, the interval flood and branch flood and the diversion system itself. And then based on analyzing of the conversion relation between risk index and investment index of diversion scheme, the risk control and conversion principals of diversion system are put forward, and the feasible diversion scheme model is built. At last, the risk and economic evaluation and scheme economic feasibility analysis method of diversion scheme are shown by an example of construction diversion scheme optimization with the discharge control condition of upstream hydropower station. The study is valuable for establishment and optimization of construction diversion scheme with upstream reservoir discharge control.
Keywords:construction diversion  cascade hydropower development  risk analysis  scheme optimization
本文献已被 CNKI 等数据库收录!
点击此处可从《工程科学》浏览原始摘要信息