大跨度钢管桁架结构施工顺序优选分析
引用本文:包雯蕾,王秀丽,崔延渊. 大跨度钢管桁架结构施工顺序优选分析[J]. 兰州理工大学学报, 2012, 38(2): 100-105
作者姓名:包雯蕾  王秀丽  崔延渊
作者单位:1. 兰州理工大学 土木工程学院,甘肃兰州730050;甘肃建筑职业技术学院,甘肃兰州730050
2. 兰州理工大学 土木工程学院,甘肃兰州,730050
3. 兰州理工大学 土木工程学院,甘肃兰州730050;甘肃省建筑设计研究院,甘肃兰州730030
摘    要:以兰州大学体育馆实际工程为背景,采用有限元软件Midas Gen对大跨度钢管桁架结构施工过程进行分析.通过对吊装过程中钢管桁架各杆的轴力和应力进行验算,验证吊装过程的安全性.首先提出从左至右、从中间至两边和从两边至中间的3种吊装施工顺序,然后针对这3种安装顺序,分别对6~17轴施工阶段结构挠度和结构应力进行分析,最后对3种安装顺序对主桁架造成的位移和应力影响进行对比.结果表明,采用从两边至中间的施工方法可以有效抵消由桁架自重引起的几何积累效应,同时配合主桁架预起拱技术,使得整个桁架结构安装达到最佳状态.

关 键 词:大跨度钢管桁架  施工顺序  优选  结构挠度  结构应力

Analysis of optimum selection of construction sequence of large-span steel tube trusses structure
BAO Wen-lei , WANG Xiu-li , CUI Yan-yuan. Analysis of optimum selection of construction sequence of large-span steel tube trusses structure[J]. Journal of Lanzhou University of Technology, 2012, 38(2): 100-105
Authors:BAO Wen-lei    WANG Xiu-li    CUI Yan-yuan
Affiliation:1,3(1.School of Civil Engineering,Lanzhou Univ.of Tech,Lanzhou 730050,China;2.Gansu Construction Vocational Technical College,Lanzhou 730050,China;3.Gansu Architectural Design and Research Institute,Lanzhou 730030,China)
Abstract:Taking the actual engineering project of gymnasium in Lanzhou University as background project,the construction procedure of its large-span steel tube trusses structure was analysed by using finite element software Midas Gen.The axial force and stress in all trussed poles in hoisting process were checked,so that the safety of hoisting process was justified.Three kinds of hoisting sequence were proposed first,namely from left to right,from middle to both ends and from both ends to middle.Then the structural deflection and structural stress during these three hoisting stages were analyzed on axes from #6 to #17.Finally,the influence of these three hoisting modes on displacement of and stress in the main truss with each other were compared.The result showed that the geometric accumulation effect induced by the weight of the tube trusses could be neutralized effectively by using the third option of hoisting sequence,i.e.from both ends to middle.Meantime,the entire tube truss structure installation could reach an optimal state with pre-arch cambering of the main truss.
Keywords:large-span steel tube trusses  construction sequence  optimum selection  structural deflection  structural stress