广州新白云机场冲孔桩施工难题及技术措施
引用本文:赵文兵,王光政.广州新白云机场冲孔桩施工难题及技术措施[J].长春工程学院学报(自然科学版),2001,2(3):41-42.
作者姓名:赵文兵  王光政
作者单位:中建八局,机械化施工公司,南京,210014
摘    要:针对新白云机场冲孔桩施工中出现的泥浆问题、卡锤、塌孔、偏孔和断桩难题,提出了一系列技术措施,使这些问题得到了彻底解决,为华南地区岩溶地层的桩基施工提供了有益的借鉴

关 键 词:岩溶地层  冲孔桩  施工难题  技术措施
文章编号:1009-8984(2001)03-0041-02
修稿时间:2001年6月8日

Construction difficulties of cast-in-situ pile in percussion drilled hole in new Guangzhou Baiyun airport project and technical countermeasures
ZHAO Wen bing,et al..Construction difficulties of cast-in-situ pile in percussion drilled hole in new Guangzhou Baiyun airport project and technical countermeasures[J].Journal of Changchun Institute of Technology(Natural Science Edition),2001,2(3):41-42.
Authors:ZHAO Wen bing  
Abstract:In accordance with the difficulties encountered during the pile construction of the new Guangzhou Baiyun airport project such as the slurry problem, hammer blocking , caving, alignment and pile segmentation, this paper puts forward a series of techmical countermeasures which have thoroughly resolved those difficulties, and therefore offers a good example for the pile construction in karst formation of South China.
Keywords:karst formation  cast  in  situ pile in percussion drilled hole  construction difficulty  technical countermeasure  