基于工程可靠度、工程造价、工期的深基坑支护结构选型研究
引用本文:段绍伟,沈蒲生.基于工程可靠度、工程造价、工期的深基坑支护结构选型研究[J].湖南科技大学学报(自然科学版),2002,17(2):79-81.
作者姓名:段绍伟  沈蒲生
作者单位:1. 湖南大学,土木工程系,湖南,长沙,410082;湘潭工学院,数理系,湖南,湘潭,411201
2. 湖南大学,土木工程系,湖南,长沙,410082
基金项目:国家自然科学基金项目资助 (编号 :0 0JJY2 0 55)
摘    要:针对目前深基坑支护结构选型缺乏科学依据 ,仅凭工程经验判定支护方法等存在的问题 ,通过分析深基坑支护工程的主要参数 ,如基坑深度、岩土性质、地下水位以及周围环境等 ,分别研究工程可靠度、工程造价、工期对支护结构选型的影响 .同时运用非结构性决策模糊集分析法 ,计算了深基坑支护结构在考虑工程可靠度、工程造价、工期时对优的相对隶属度 .由于相同的深基坑支护工程 ,不同的支护结构型式对优的相对隶属度不同 ,据此可进行深基坑支护结构选型的判定 .通过工程实例论证 ,该理论方法新颖 ,工程应用可靠 ,且适用于公路、桥梁、水利等工程的方案优化研究 .图 1,表 1,参 5 .

关 键 词:深基坑支护  相对隶属度  模糊优化
文章编号:1000-9930(2002)02-0079-03
修稿时间:2001年9月5日

Study on selection of braced structures of deep-excavation pit considering construction reliability, cost and time limited
DUAN Shao-wei ,SHEN PU-sheng.Study on selection of braced structures of deep-excavation pit considering construction reliability, cost and time limited[J].Journal of Hunan University of Science & Technology(Natural Science Editon),2002,17(2):79-81.
Authors:DUAN Shao-wei    SHEN PU-sheng
Institution:DUAN Shao-wei 1,2,SHEN PU-sheng 1
Abstract:The problems which the present selection of braced structures lack scientific evidence, only depend on engineering experiences are analysised firstly, then the influence of construction reliability, cost and time limited on the selection of braced structures are studied by analyzing the main parameters of deep excavation pit,such as the depth of excavation pit,the properties of soil, the situation of under warter and environment.The optimization of relative membership degree for braced structures of deep-excavation are also calculated,with the construction reliability, cost and time limited considered, by using a non-structural decision making with fuzzy set analysis in this paper. To the same braced structure of deep-excavation pits, the optimization of relative membership degree for unlikely braced structure pattern are differences, therefore it is very easy to select the pattern of braced structures. The method has been proved novel and reliable by practical case and can be applied to the project optimization study of highway,bridge and water conservancy engineering.1fig.,1tab.,5refs.
Keywords:braced structures of deep-excavation  relative membership degree  fuzzy optimization