BF公司L6生产线快速换型效率改善分析
引用本文:马如宏,董晓慧,张溪红,孙凯南.BF公司L6生产线快速换型效率改善分析[J].盐城工学院学报(自然科学版),2017,30(3):41-47.
作者姓名:马如宏  董晓慧  张溪红  孙凯南
作者单位:盐城工学院 机械工程学院, 江苏 盐城 224002;盐城工学院 机械工程学院, 江苏 盐城 224002;盐城工学院 机械工程学院, 江苏 盐城 224002;盐城工学院 机械工程学院, 江苏 盐城 224002
摘    要:针对BF公司L6生产线快速换型流程中的换料效率低、预装工位待料频繁问题,基于精益生产思想中的快速换型理论,采用价值流图析、意大利面条图等方法,通过设计工位物料清单来缩减换料时间,提升换料效率;通过设计换型信息提示灯来优化换型信息流;通过设计新的料架,减少工序调整的换型时间,并对现有快速换型流程进行优化,使整个换型效率得到很大提升。L6生产线评价结果显示,采用新的方法,不同系列产品175D0、38100的换型时间从17.9min缩减至6.2 min,换型效率提升了65.4%。

关 键 词:快速换型  精益生产  价值流图析
收稿时间:2017/5/22 0:00:00

Research on the Efficiency Improvement of SMED in BF's Production Line
MA Ruhong,DONG Xiaohui,ZHANG XIhong and SUN Kainan.Research on the Efficiency Improvement of SMED in BF''s Production Line[J].Journal of Yancheng Institute of Technology(Natural Science Edition),2017,30(3):41-47.
Authors:MA Ruhong  DONG Xiaohui  ZHANG XIhong and SUN Kainan
Institution:School of Mechanical Engineering, Yancheng Institute of Technology, Yancheng Jiangsu224051, China;School of Mechanical Engineering, Yancheng Institute of Technology, Yancheng Jiangsu224051, China;School of Mechanical Engineering, Yancheng Institute of Technology, Yancheng Jiangsu224051, China;School of Mechanical Engineering, Yancheng Institute of Technology, Yancheng Jiangsu224051, China
Abstract:Aim at the problems in the L6 production line of BF company such as the low efficiency of refueling and the frequent replacement of the pre-installed station, based on the theory of SMED in lean production, by using the value stream mapping, spaghetti diagram method, the change type information lamp is designed to optimize the change information flow. Through the design of new material rack, the changeover time of process adjustment is reduced. And through the optimization of the existing SMED process, the whole change efficiency has been greatly improved. L6 production line evaluation results show that by using new methods, the changeover time of different series products such as 175D0 and 38100 is reduced from 17. 9min to 6. 2 min, and the transfer efficiency is increased by 65. 4%.
Keywords:SMED  Lean Production  Value Stream Mapping