高流速卵石地层地铁联络通道人工冻结温度场研究
引用本文:韩昀希,冯利华,任全军,沈宇鹏,刘欣. 高流速卵石地层地铁联络通道人工冻结温度场研究[J]. 科学技术与工程, 2024, 24(12): 5134-5142
作者姓名:韩昀希  冯利华  任全军  沈宇鹏  刘欣
作者单位:北京交通大学 土木工程学院 北京;中铁一局集团第二工程有限公司
基金项目:国家自然科学(42172291);北京市自然科学基金资助项目(8212014);中央高校基本科研业务费专项资金资助(2023JBZY026)
摘    要:地铁联络通道的开挖经常受到地下水干扰,人工地层冻结法凭借其优秀的封水性和适应性成为富水地层联络通道施工的首选工法。依托北京地铁12号线苏州桥站~人民大学站区间1#联络通道冻结工程,通过现场实测研究地层温度场和泄压孔压力的发展规律,分析冻结帷幕的交圈特征,确定高流速地层冻结壁薄弱位置。结果表明:盐水去回路温度在冻结初期迅速下降,而后降速减缓并最终稳定在-28℃以下;测温孔中土体与管片交界处的温度高于土体内部,渗流上游冻结壁温度高于下游,这些区域应当重点监测;冻结至59d时,利用基于实际降温速率的分阶段冻结壁厚度计算方法求得不同截面位置处的冻结壁最小厚度为2 495.2mm,同时泄压孔压力已全部释放并保持稳定,冻结壁不再发展,满足联络通道开挖要求。研究成果能为高流速地层的人工冻结参数选取和监测提供理论支持。

关 键 词:联络通道;人工地层冻结法;温度场;冻结壁厚度;冻胀力
收稿时间:2023-06-28
修稿时间:2023-10-25

Research on Subway Cross Passage Artificial Freezing Temperature Field in Pebble Stratum with High Velocity Flow
Han Yunxi,Feng Lihu,Ren Quanjun,Shen Yupeng,Liu Xin. Research on Subway Cross Passage Artificial Freezing Temperature Field in Pebble Stratum with High Velocity Flow[J]. Science Technology and Engineering, 2024, 24(12): 5134-5142
Authors:Han Yunxi  Feng Lihu  Ren Quanjun  Shen Yupeng  Liu Xin
Affiliation:School of Civil Engineering, Beijing Jiaotong University, Beijing
Abstract:The excavation of subway cross passage is often disturbed by groundwater, and the artificial ground freezing method has become the preferred method for the construction of cross passage in water-rich stratum by virtue of its excellent water sealing and adaptability. Relying on the freezing project of 1# cross passage between Suzhou Qiao Station and Renmin Univ. Station of Beijing Metro Line 12, the development law of stratum temperature field and the pressure of depressurization hole was studied through field monitoring. The closure characteristics of freezing curtain were analyzed to determine the weak position of freezing wall of high flow velocity stratum. The results show that: the temperature of brine decreases rapidly in the early stage of freezing, then the rate of decrease slows down and finally the temperature stabilizes below -28℃. The temperature at the junction of soil and tunnel lining in the thermometric holes is higher than that inside of the soil, and the temperature of the freezing wall at the upstream of the seepage is higher than that at the downstream, so these areas should pay more attention to monitor. When freezing to 59 d, based on the actual rate of decrease in temperature, the calculation method of the freezing wall thickness in different stages was used to obtain the minimum thickness of the freezing wall in different section is 2 495.2 mm. At the same time, the pressure of depressurization hole has been fully released and kept stable, the frozen wall no longer develops, and meets the requirements of cross passage excavation. The research results can provide theoretical support for the selection of artificial freezing parameters and monitoring in high flow velocity strata.
Keywords:cross passage;artificial ground freezing method;temperature field;freezing wall thickness;frost heaving force