大化水电站二期导流工程导流明渠泥沙运动与冲淤
引用本文:王涛.大化水电站二期导流工程导流明渠泥沙运动与冲淤[J].广西科学,1995,2(2):67-73.
作者姓名:王涛
作者单位:广西水电工程局
摘    要:大化水电站二期导流工程截流前,导流明渠基本堵塞,靠人力及机械清淤无法按时实现截流。经过分析研究,采用主河槽预抛方案提高上游水位,使导流明渠水流速由1.0m/s逐渐增大到3.25m/s,在17天内冲走25.2万m3淤积泥砂,实现了按计划截流。

关 键 词:大化水电站,起动流速,导流明渠,泥沙运动,冲淤
收稿时间:1994/4/8 0:00:00
修稿时间:1994/8/3 0:00:00

Sediment Sluicing& Sediment Motion for Construction Diversion of Second Stage on the Dahua Hydropower Station
Wang Tao.Sediment Sluicing& Sediment Motion for Construction Diversion of Second Stage on the Dahua Hydropower Station[J].Guangxi Sciences,1995,2(2):67-73.
Authors:Wang Tao
Institution:Guangxi Hydroelectric Construction Bureau, 1 Mingxiu Road, Nanning, Guangxi, 530001
Abstract:The amount of sediment in the diversion channel of Dahua hydropower station reached 252 000 m3 which almost blocked up the channel before the second stage of river-damming of diversion construction. Clearing away the sediment by manpower and machine could not realize the riverdamming in a planned way. The employ of throw stones in advance to main river led scheme raisedthe water level of upper reaches and increased the waterflow velocity of diversion channel from1. 0 m/s to 3. 25 m/s, which resulted in the sluicing away of 252 000 m3 sediment within 17 days.Thus damming the river was achieved in a planned way.
Keywords:Dahua hydropower station  incipient velocity  diversion channel  sediment motion  sluicing sediment  