基于资源流网络与时间缓冲集成优化的鲁棒性项目调度
引用本文:崔南方,梁洋洋. 基于资源流网络与时间缓冲集成优化的鲁棒性项目调度[J]. 系统工程理论与实践, 2018, 38(1): 102-112. DOI: 10.12011/1000-6788(2018)01-0102-11
作者姓名:崔南方  梁洋洋
作者单位:华中科技大学 管理学院, 武汉 430074
基金项目:国家自然科学基金(71271097)
摘    要:针对工期不确定的资源受限项目调度问题,将鲁棒性资源分配和时间缓冲插入两种方法进行有效地结合,通过设计两阶段集成优化算法构建抗干扰能力较强的鲁棒性项目调度计划.第一阶段提出MEPC(minimizing expected penalty cost)资源流网络优化算法,通过对资源进行有效配置生成稳定的资源流网络.为进一步提升调度计划的鲁棒性,第二阶段通过固定第一阶段构建的资源流网络,设计EPC(expected penalty cost)缓冲优化算法,通过迭代方式在延期风险较大的活动前插入时间缓冲,实现项目期望惩罚成本最小化.最后通过大规模仿真实验从解鲁棒性质鲁棒性两方面来验证两阶段算法的有效性和可行性,结果表明通过将资源流网络与时间缓冲进行集成优化构建的调度计划不仅具有较好的完工性并且能更有效地应对项目执行过程中各种不确定性因素的干扰.

关 键 词:鲁棒性  资源流网络  时间缓冲  期望惩罚成本  集成优化  
收稿时间:2016-04-11

Robust project scheduling based on the integrated optimization between resource flow network and time buffers
CUI Nanfang,LIANG Yangyang. Robust project scheduling based on the integrated optimization between resource flow network and time buffers[J]. Systems Engineering —Theory & Practice, 2018, 38(1): 102-112. DOI: 10.12011/1000-6788(2018)01-0102-11
Authors:CUI Nanfang  LIANG Yangyang
Affiliation:School of Management, Huazhong University of Science and Technology, Wuhan 430074, China
Abstract:For solving the resource constrained project scheduling problem (RCPSP) with stochastic durations, robust resource allocation and time buffer insertion are combined effectively. A two-stage integrated optimization algorithm is proposed to generate robust project schedules against disruptions. In the first stage, a myopic expected penalty cost (MEPC) procedure is designed to construct a stable resource flow network by efficiently allocating resources among project activities. To further improve the schedule stability, an expected penalty cost (EPC) algorithm that relies on the fixed resource flow network is proposed in the second stage to minimize the expected penalty cost through inserting time buffers in front of the activities with higher delay risks. Finally, extensive computational experiments are performed to verify the feasibility and effectiveness of the two-stage algorithm from two aspects of solution robustness and quality robustness. The results indicate that the project schedule generated by the integration of the resource flow network and time buffers not only can achieve shorter completion times, but also can deal with disruptions more effectively during project execution.
Keywords:robust  resource flow network  time buffers  expected penalty cost  integrated optimization  