三峡工程建设与运行期建筑物安全监测资料分析
引用本文:杨爱明,段国学,马能武.三峡工程建设与运行期建筑物安全监测资料分析[J].工程科学,2011,9(7):117-122.
作者姓名:杨爱明  段国学  马能武
作者单位:长江水利委员会长江勘测规划设计研究院,武汉430010;长江水利委员会长江勘测规划设计研究院,武汉430010;长江水利委员会长江勘测规划设计研究院,武汉430010
摘    要:以三峡工程17年的安全监测资料为依据,论述了各主要建筑物在施工建设及运行期变形、渗流渗压及应力应变的变化规律,细致分析和评价了各建筑物在不同施工阶段、不同环境状态下的运行状态及安全特征。监测结果表明:在分期蓄水及运行阶段,库水位的反复消长对大坝的变形有一定的影响;大坝基础的渗漏量在逐渐减少;高强度的开挖卸荷对岩石高边坡的变形影响明显;开挖结束后,高边坡变形快速收敛,船闸建筑物的变形较小,高耸建筑物及船闸建筑物表现出了明显的随温度变化的规律。得出了三峡工程各项安全指标在设计允许范围内建筑物运行安全等重要结论。

关 键 词:三峡工程  建筑物  安全监测  资料分析

The analysis on structure safety monitoring data of Three Gorges Project in construction and operation
Yang Aiming,Duan Guoxue and Ma Nengwu.The analysis on structure safety monitoring data of Three Gorges Project in construction and operation[J].Engineering Sciences,2011,9(7):117-122.
Authors:Yang Aiming  Duan Guoxue and Ma Nengwu
Abstract:Based on 17 year monitoring data of the Three Gorges Project (TGP), the change laws of deformation, seepage flow and pressure, as well as stress and strain of the main structures in the period of construction and operation are discussed. Meanwhile, the operational status and safety features of various structures in different construction stages and under different circumstances are analyzed and evaluated in detail. The monitoring results show that the repeated rise and fall of reservoir water level affect the deformation of dam in storage and operation stages; the leakage of dam foundation reduces gradually; the high intensity excavation unloading influences the deformation of high rock slope significantly. After the excavation, the deformation of high rock slope rapidly decreases,while the deformation of ship lock is small,but they all vary with temperature obviously. It is concluded that the safety indexes of TGP are within the allowable range of design and the structures are safe in operation.
Keywords: