沙湾水电站尾水渠砼面板施工
引用本文:黄志军. 沙湾水电站尾水渠砼面板施工[J]. 科技情报开发与经济, 2010, 20(6): 149-152
作者姓名:黄志军
作者单位:中铁二十二局集团第五工程有限公司,重庆,400042
摘    要:沙湾水电站尾水渠工程是迄今为止亚洲水电站建设之中设计长度最长的尾水渠。介绍了砼面板防裂配合比设计、施工质量控制、滑模的设计和配重计算、模体的加工和安装以及模板的支撑和操作等,为同类施工提供了借鉴。

关 键 词:沙湾水电站  尾水渠  砼面板  施工质量  滑模设计

Talking about the Concrete Panel Construction in the Tailrace of Shawan Hydropower Station
HUANG Zhi-jun. Talking about the Concrete Panel Construction in the Tailrace of Shawan Hydropower Station[J]. Sci-Tech Information Development & Economy, 2010, 20(6): 149-152
Authors:HUANG Zhi-jun
Affiliation:HUANG Zhi-jun
Abstract:So far,the tailrace engineering of Shawan Hydropower Station is the one with longest design length in the construction of Asian hydropower stations.This paper mainly introduces the anti-cracking concrete panel design,construction quality control,sliding formwork design and weight calculation,processing and installation of die body,and the support and operation of the template,etc.which provides the reference for the similar construction.
Keywords:Shawan Hydropower Station  tailrace  concrete panel  construction quality  sliding formwork design  