基坑开挖对下卧管线竖向变形影响的数值分析
引用本文:吴峥,姚黎芳,陈学良,张恒志,徐长节.基坑开挖对下卧管线竖向变形影响的数值分析[J].科学技术与工程,2021,21(7):2843-2849.
作者姓名:吴峥  姚黎芳  陈学良  张恒志  徐长节
作者单位:杭州市市政设施监管中心,杭州 310003;浙江大学滨海和城市岩土工程研究中心,杭州 310058;浙江大学滨海和城市岩土工程研究中心,杭州 310058;华东交通大学-土木工程国家实验教学示范中心,南昌 330013;华东交通大学江西省岩土工程基础设施安全与控制重点实验室,南昌 330013
基金项目:国家杰出青年科学基金(51725802), 国家自然科学基金项目(51878276), 浙江省自然科学基金委员会-华东院联合基金(LHZ19E080001), 国家自然科学基金-高铁联合基金(U1934208)
摘    要:基坑开挖会对下卧管线产生不利影响,如何控制基坑开挖对下卧管线产生的不利影响是工程界的热点问题.以杭州市沿江大道管廊基坑上跨污水管段工程为背景,利用ABAQUS软件进行数值模拟,建立了三维有限元模型.在此基础上分析了管线周围土体注浆加固的作用,同时研究了改变管线与基坑的夹角引起管线竖向位移的变化规律.分析结果表明:上方基坑的开挖会使下卧管线呈现出"中间大、两边小"的"上凸型"变形模式,对下卧基坑管线周围进行合理的注浆加固,能有效减少管线的整体隆起变形;且下卧管线与基坑长边夹角越大,管线的最大隆起位移越小,当管线与基坑长边垂直时,管线的隆起变形最小.研究结果可为今后类似工程提供借鉴.

关 键 词:基坑  数值分析  管线  隆起位移
收稿时间:2020/6/4 0:00:00
修稿时间:2020/12/21 0:00:00

Numerical Analysis on Influence of the Foundation Pit Excavation on the Vertical Deformation of Subjacent Pipelines
Wu Zheng,Yao Lifang,Chen Xueliang,Zhang Hengzhi,Xu Changjie.Numerical Analysis on Influence of the Foundation Pit Excavation on the Vertical Deformation of Subjacent Pipelines[J].Science Technology and Engineering,2021,21(7):2843-2849.
Authors:Wu Zheng  Yao Lifang  Chen Xueliang  Zhang Hengzhi  Xu Changjie
Institution:Hangzhou Municipal Facilities Supervision Center,,,,
Abstract:The excavation of foundation pit will inevitably cause adverse effects on the subjacent pipeline. How to reduce this effect is a very important problem. In this paper, based on the project of the foundation pit excavation of Yanjiang Avenue in Hangzhou, ABAQUS software was used for numerical simulation, and a three-dimensional finite element model was established. On this basis, the effect of grouting reinforcement of soil around the pipeline was analyzed. By changing the angle between the pipeline and the foundation pit, the influence of the angle change on the vertical deformation of the pipeline was studied. The analysis results show that the excavation of foundation pit will make the underlying pipeline present a convex deformation mode of "large in the middle and small on both sides". The reasonable grouting reinforcement around the underlying foundation pit pipeline can effectively reduce the overall uplift deformation of the pipeline, and the larger the intersection angle between the underlying pipeline and the long side of the foundation pit, the smaller the maximum uplift displacement of the pipeline. The research results of this paper can provide reference for similar projects in the future.
Keywords:foundation pit      numerical analysis      pipeline      heave deformation
本文献已被 CNKI 万方数据 等数据库收录!