岩石巷道二阶二段掏槽爆破优化分析
引用本文:张渊通,汤文达,郭盛华,康一强,王济祥.岩石巷道二阶二段掏槽爆破优化分析[J].科学技术与工程,2020,20(11):4273-4278.
作者姓名:张渊通  汤文达  郭盛华  康一强  王济祥
作者单位:中国矿业大学(北京)力学与建筑工程学院,北京100083;阳泉煤业(集团)股份有限公司一矿,阳泉045000
基金项目:国家重点研发计划;高等学校学科创新引智计划计划)
摘    要:为了解决因矸石过大而导致出矸时间过长,进而影响整个巷道掘进的问题,基于应力波叠加原理和二阶二段掏槽技术,提出通过采用多阶段一次爆破的方式,对现有的爆破和施工参数设计进行优化,然后从分形的角度对爆堆进行分析。经过现场试验和块度分析后发现:多阶段掏槽一次爆破可以有效地控制矸石粒级分布,平均块度直径减小了5 cm,矸石大块率明显降低,分形维数有所增加;大幅度缩减出矸时间和打眼装药时间,分别减少30、60 min;月循环进尺提高22.2%,有效地保障了硬岩巷道的掘进效率。

关 键 词:二阶二段  应力波叠加  掏槽技术  分形维数
收稿时间:2019/7/22 0:00:00
修稿时间:2019/12/26 0:00:00

Optimization Analysis of Two-step cutting blasting on Rock Roadway
Zhang Yuantong,Tang Wend,Guo Shenghu,Kang Yiqiang,Wang Jixiang.Optimization Analysis of Two-step cutting blasting on Rock Roadway[J].Science Technology and Engineering,2020,20(11):4273-4278.
Authors:Zhang Yuantong  Tang Wend  Guo Shenghu  Kang Yiqiang  Wang Jixiang
Institution:School of Mechanics Civil Engineering,China University of Mining TechnologyBeijing,School of Mechanics Civil Engineering,China University of Mining TechnologyBeijing,School of Mechanics Civil Engineering,China University of Mining TechnologyBeijing,School of Mechanics Civil Engineering,China University of Mining TechnologyBeijing
Abstract:In order to solve the problem that the gangue transport time is too long due to the large size, and then influences the tunneling of the whole roadway, based on the principle of stress wave superposition and the two-step cutting technology, a multi-stage one-time blasting method is proposed. The blasting parameters are optimized, the blasting result is analyzed from Fractal Dimension. After field test and block analysis, it is found that the multi-stage one-time blasting can effectively control the distribution of block size, the average block diameter is reduced by 5 cm, the large block rate is obviously decreased, and the fractal dimension is increased; the time of gangue transportation and drilling&charging were reduced by 30 minutes and 60 minutes respectively; the monthly footage was increased by 22.2%, ensuring the tunneling efficiency of the hard rock roadway.
Keywords:two-step    stress-wave superposition    cutting technology    fractal dimension