向家坝水电站混凝土浇筑VR与智能进度模拟系统设计
引用本文:周厚贵,;戴志清,;张开广,;孙昌忠,;曹生荣.向家坝水电站混凝土浇筑VR与智能进度模拟系统设计[J].三峡大学学报(自然科学版),2014(4):1-5.
作者姓名:周厚贵  ;戴志清  ;张开广  ;孙昌忠  ;曹生荣
作者单位:[1]中国能源建设集团有限公司,北京100029; [2]中国葛洲坝集团股份有限公司,湖北宜昌443002; [3]水资源与水电工程科学国家重点实验室(武汉大学),武汉430072
基金项目:中央高校基本科研业务费专项资金资助项目(5082022);湖北省自然科学基金项目(2009CDZ038)
摘    要:针对向家坝水电站大坝混凝土浇筑施工工程量大、工期长、设备多、关系复杂等特点以及提高施工管理与决策科学性和效率的现实需求出发,以虚拟现实和人工智能领域的知识工程为理论基础,开发了向家坝水电站混凝土浇筑VR与智能进度模拟系统,并应用于工程实践.介绍了该系统的需求分析与实现思路、整体结构设计、系统功能设计以及系统实现的主要技术方案等研究成果,以期为相关工作提供参考和借鉴.工程实践应用表明,本系统具有形象性、智能化、综合化等优势,对于保证向家坝水电站大坝混凝土浇筑施工具有重要的实践价值.

关 键 词:向家坝水电站  施工模拟  人工智能  虚拟现实  系统设计

System Design for Virtual Reality and Intelligence Schedule Simulation of Concrete Pouring at Xiangj iaba Hydropower Station
Zhou Hougui;Dai Zhiqing;Zhang Kaiguang;Sun Changzhong;Cao Shengrong.System Design for Virtual Reality and Intelligence Schedule Simulation of Concrete Pouring at Xiangj iaba Hydropower Station[J].Journal of China Three Gorges University(Natural Sciences),2014(4):1-5.
Authors:Zhou Hougui;Dai Zhiqing;Zhang Kaiguang;Sun Changzhong;Cao Shengrong
Institution:Zhou Hougui, Dai Zhiqing, Zhang Kaiguang, Sun Changzhong, Cao Shengrong(1. China Energy Engineering Group Co. , Ltd. , Beijing 100029, China;2. China Gezhouba Group Co. , Ltd. , Yichang 443002, Chins; 3. State Key Laboratory of Water Resources & Hydropower Engineering Science, Wuhan Univ., Wuhan 430072, China)
Abstract:In light of the fact that concrete pouring in Xiangj iaba hydropower station has the characteristics of large quantity of construction works,long durations,multi-facility,complex correlation,etc.;as well as the needs of improving the efficiency and the scientific nature of management and decision,a system for virtual re-ality and intelligent progress simulation of concrete pouring on Xiangjiaba hydropower station is developed and applied to engineering practice on the theoretical basis of knowledge engineering in the fields of virtual reality and artificial intelligence.Some research achievements including the requirement analysis and implementation idea of the system,the main technical schemes of the integral structure design,the system function design and system implementation,etc.are introduced,so as to provide reference for related works.The application to engineering practice shows that this system has the advantages of vividness,intelligence and integration, which is of great practical value to ensure the construction safety of concrete pouring in Xiangj iaba hydropow-er station.
Keywords:Xiangj iaba hydropower station  construction simulation  artificial intelligence  virtual real-ity  system design