部分地锚斜拉桥经济性能分析
引用本文:孙斌,肖汝诚,CAI C S.部分地锚斜拉桥经济性能分析[J].同济大学学报(自然科学版),2013,41(10):1476-1482.
作者姓名:孙斌  肖汝诚  CAI C S
作者单位:同济大学桥梁工程系,同济大学桥梁工程系,路易斯安那州立大学土木与环境工程系/长沙理工大学土木与建筑学院
基金项目:国家自然科学基金(51008223)
摘    要:将部分地锚斜拉桥分为拉索、主塔、主梁、锚碇、基础等五部分, 分别推导了其材料用量计算公式, 引入材料单价系数得到了全桥总造价和单位桥面面积造价. 据此开展了该桥型经济性能参数研究, 得到了主要结构参数的最优取值, 即地锚与中跨跨径之比为0.3~0.4, 边中跨比为0.40~0.45, 塔跨比为0.15~0.20. 对比结果表明, 随锚碇处地质条件不同, 在主跨跨径超过800~1600 m后, 部分地锚斜拉桥的经济性能优于全自锚斜拉桥.

关 键 词:部分地锚斜拉桥    经济性能    材料用量    参数研究    地锚与中跨跨径之比
收稿时间:5/9/2012 12:00:00 AM
修稿时间:7/9/2013 12:00:00 AM

Cost Analysis of Partially Earth anchored Cable stayed Bridge
SUN Bin,XIAO Rucheng and CAI C S.Cost Analysis of Partially Earth anchored Cable stayed Bridge[J].Journal of Tongji University(Natural Science),2013,41(10):1476-1482.
Authors:SUN Bin  XIAO Rucheng and CAI C S
Institution:Department of Bridge Engineering, Tongji University,Department of Bridge Engineering, Tongji University,Department of Civil and Environmental Engineering, Louisiana State University/School of Civil Engineering and Architecture, Changsha University of Science and Technology
Abstract:The equations for material amounts of all structural parts in partially earth-anchored cable-stayed bridges were derived, including the stay cables, pylons, girders, anchorages, and foundations. The cost of both the entire bridge and per unit area of the deck was obtained by introducing the cost of per unit weight of each material. Then, parametric studies were performed from an economic behavior perspective, and suggested parameter values were obtained as: the ratio of the earth-anchored girder length to the main span length is 0.3 to 0.4; the ratio of the side span length to the total self-anchored girder length in the main span is 0.4 to 0.45; and the ratio of the height of the pylon above the girder to the main span length is 0.15 to 0.2. The comparisons of results show that the partially earth-anchored cable-stayed bridge is more economical than the fully self-anchored cable-stayed bridge with a main span length over 800-1600 m, of which the threshold depends on the geological conditions at the anchorages.
Keywords:partially earth-anchored cable-stayed bridge  cost analysis  material amounts  parametric study  earth-anchored part length
点击此处可从《同济大学学报(自然科学版)》浏览原始摘要信息
点击此处可从《同济大学学报(自然科学版)》下载免费的PDF全文