基于关键链和混合优化算法的舰船多项目并行建造进度管理方法
引用本文:巩军,胡涛,刘生学.基于关键链和混合优化算法的舰船多项目并行建造进度管理方法[J].系统工程与电子技术,2020,42(8):1784-1793.
作者姓名:巩军  胡涛  刘生学
作者单位:1. 海军工程大学管理工程与装备经济系, 湖北 武汉 4300332. 海军工程大学舰船综合试验训练基地, 湖北 武汉 430033
基金项目:国家自然科学基金(71501183)
摘    要:针对舰船多资源约束、多项目并行建造条件下进度优化与管理能力的不足,提出了一套进度管理方法。首先,基于关键链理论给出了多资源约束下舰船多项目并行建造进度管理步骤。其次,构建了舰船多项目并行建造进度优化模型,可实现在优化并行项目总工期的过程中通过合理分配各种资源获取最佳项目实施组合。最后,设计了适合于舰船建造等大型复杂工程项目求解的混合优化算法,并通过算例验证了方法的实用性。

关 键 词:关键链  多项目  并行建造  进度管理  智能算法  
收稿时间:2019-10-11

Schedule management method of warships multi-project parallel construction based on critical chain and hybrid optimization algorithm
Jun GONG,Tao HU,Shengxue LIU.Schedule management method of warships multi-project parallel construction based on critical chain and hybrid optimization algorithm[J].System Engineering and Electronics,2020,42(8):1784-1793.
Authors:Jun GONG  Tao HU  Shengxue LIU
Institution:1. Department of Management Engineering and Equipment Economics, Naval University of Engineering, Wuhan 430033, China2. Base of Ship Comprehensive Test Training, Naval University of Engineering, Wuhan 430033, China
Abstract:Aiming at the deficiency of schedule optimization and management ability under the condition of multi-resource constraints and multi-project parallel construction of warships, a set of schedule management methods is proposed. Firstly, based on the critical chain theory the schedule management steps of warships multi-project parellel construction under multiresource constraints are given. Secondly, schedule optimization models of warships multi-project parallel construction are constructed, which can achieve the optimal project implementation portfolio by allocating various resources reasonably in the process of optimizing the total construction period of parallel projects. Finally, a hybrid optimization algorithm is designed for solving the large-scale compolex engineering projects such as ship construction. The practicability of the method is verified by an example.
Keywords:critical chain  multi-project  parallel construction  schedule management  intelligent algorithm  