浅议立井井筒过含水段时工作面预注浆的施工方法
引用本文:杨振华,付建党.浅议立井井筒过含水段时工作面预注浆的施工方法[J].科学之友,2011(18).
作者姓名:杨振华  付建党
作者单位:平煤六矿通风科;平顶山工业职业技术学院;
摘    要:平煤六矿北风井井筒掘进到378m位置时,工作面开始涌水,最大涌水量达到100m3/h,无法进行掘进施工。根据对涌水情况和地质条件的分析,决定采用工作面预注浆技术治理涌水。经工作面预注浆,井筒涌水量降到了2m3/h以下,取得了良好效果。

关 键 词:井筒  预注浆  含水层  浆液浓度  

On the Shaft When the Face Over Water Segment of the Construction Method of Pre-grouting
Yang Zhenhua,Fu Ji,ang.On the Shaft When the Face Over Water Segment of the Construction Method of Pre-grouting[J].Friend of Science Amateurs,2011(18).
Authors:Yang Zhenhua  Fu Ji  ang
Institution:Yang Zhenhua,Fu Jiandang
Abstract:Pingdingshan six mine north Shaft position heading into the 378 m,the face began gushing water,the maximum water inflow to 100 m3/h,the construction can not be boring.Based on the gushing water and geological conditions of the analysis of the situation,decided to adopt a pre-grouting technology governance face gushing water.The face pre-grouting,borehole water inflow dropped to 2 m3/h or less,and achieved good results.
Keywords:shaft  pre-grouting  aquifer  slurry concentration  