首山一矿聚能双掏槽光面爆破技术应用
引用本文:冀畔俊,娄渊沛,汪宾,范航,李宗泽.首山一矿聚能双掏槽光面爆破技术应用[J].科学技术与工程,2022,22(7):2648-2653.
作者姓名:冀畔俊  娄渊沛  汪宾  范航  李宗泽
作者单位:河南平宝煤业有限公司;重庆大学煤矿灾害动力学与控制国家重点实验室
摘    要:为适应平宝公司岩巷掘进的巨大需求,满足矿井采掘布局的进一步优化需要。针对岩巷掘进施工时打眼多、装药多、光面爆破效果差、工效低的现状,分析了原有爆破方式施工存在的问题及原因,在常规岩巷光面爆破的基础上,利用理论分析,室内试验,现场试验等手段,研究开发了聚能水压双掏槽光面爆破技术。并在平宝公司首山一矿进行了应用。工程实践表明,该方法大幅度降低炮眼掘进量,雷管、炸药等消耗量,降低爆破材料费。有效提升了岩巷光面爆破效果、增加了循环炮进率,岩巷光爆效果得到了明显的提升。在相同的条件下进尺效率得到了提高,在满足工程质量的同时,降低了施工成本,更加的节能环保。

关 键 词:掘进    聚能水压    双掏槽    光面爆破  
收稿时间:2021/6/2 0:00:00
修稿时间:2021/12/9 0:00:00

Application of Shaped Charge Double Cut Smooth Blasting Technology in Shoushan No.1 Coal Mine
Ji Panjun,Lou Yuanpei,Wang Bin,Fan Hang,Li Zongze.Application of Shaped Charge Double Cut Smooth Blasting Technology in Shoushan No.1 Coal Mine[J].Science Technology and Engineering,2022,22(7):2648-2653.
Authors:Ji Panjun  Lou Yuanpei  Wang Bin  Fan Hang  Li Zongze
Institution:Henan Pingbao Coal Co,Ltd; State Key Laboratory of Coal Mine Disaster Dynamics and Control,Chongqing University
Abstract:In order to meet the huge demand of rock roadway excavation in pingbao company and further optimize the layout of mine excavation. In view of the current situation of more drilling, more charging, poor smooth blasting effect and low work efficiency in rock roadway excavation construction, Analyzed the problems and causes of the original blasting method construction, on the basis of conventional smooth blasting in rock roadway, the technology of shaped energy water pressure double cut smooth blasting is researched and developed. It has been applied in Shoushan No.1 mine of pingbao company. By using theoretical analysis, indoor tests, field tests. The engineering practice shows that this method effectively improves the smooth blasting effect of rock roadway, increases the cycle blasting rate, and the smooth blasting effect of rock roadway is obviously improved, This method significantly reduces the amount of borehole boring, the consumption of detonators, explosives, etc., and reduces the cost of blasting materials. Under the same conditions, the footage efficiency has been improved, while meeting the engineering quality, the construction cost has been reduced, and it is more energy-saving and environmental protection.
Keywords:tunnelling  shaped charge water pressure  double cut  smooth blasting