中洞法连拱隧道施工稳定性分析及优化
引用本文:徐波,杨旺兴,李加加,刘涛影,张朝阳.中洞法连拱隧道施工稳定性分析及优化[J].科学技术与工程,2022,22(2):812-820.
作者姓名:徐波  杨旺兴  李加加  刘涛影  张朝阳
作者单位:中铁建华南建设有限公司;中铁十六局集团北京轨道交通工程建设有限公司;中南大学资源与安全工程学院
摘    要:针对中洞法连拱隧道暗挖施工的稳定性问题,依托广州大道中站工程实例,综合分析了开挖过程拱顶沉降、底部变形、洞周收敛、初支结构应力、中隔墙应力以及地表沉降等指标的动态响应特征,总结了不同工艺参数下隧道变形规律,结果表明:拱顶沉降最大值和最大沉降速率以及底部隆起最大值均在后行洞,而先行洞洞周收敛值最大,为1.59 mm;侧洞...

关 键 词:中洞法  连拱隧道  动态响应  变形规律
收稿时间:2021/4/16 0:00:00
修稿时间:2021/11/15 0:00:00

Stability Analysis and Optimization of Double-arch Tunnel Constructed by Center Drift Method
Xu Bo,Yang Wangxing,Li Jiaji,Liu Taoying,Zhang Chaoyang.Stability Analysis and Optimization of Double-arch Tunnel Constructed by Center Drift Method[J].Science Technology and Engineering,2022,22(2):812-820.
Authors:Xu Bo  Yang Wangxing  Li Jiaji  Liu Taoying  Zhang Chaoyang
Institution:China Railway Bureau Group Beijing Metro Engineering Construction Co,Ltd; School of Resources and Safety Engineering,Central South University
Abstract:Aiming at the stability of the excavation of the double-arch tunnel with the center drift method, relying on the Guangzhou Avenue middle station project, the dynamic response characteristics of the arch settlement, bottom deformation, tunnel convergence, initial support structure and partition wall stress, and surface settlement during the excavation process are comprehensively analyzed, and the deformation law of tunnel under different technological parameters is summarized. The results show that the maximum settlement and settlement rate of the vault, and the maximum bottom uplift are in the posterior tunnel, while the convergence value of the prior tunnel is the largest at 1.59 mm; the supporting structure of the upper step close to the middle hole is under tension, while that of the upper step far from the middle hole is under pressure; the middle part of the partition wall is subjected to compressive stress, while the top and bottom longitudinal beam bear both tensile stress and compressive stress; the maximum ground settlement is located in the center of the tunnel, which is 7.20 mm, and the radius of the affected area of tunnel construction is about 25 m; the stability of the tunnel decreases with the increase of the distance between the upper and lower steps of the middle hole and the adjacent steps of the side hole, and it increases with the increase of the distance between the side holes.
Keywords:Center drift method  Double-arch tunnel  Dynamic response  Deformation law