项目附加资源优化的整数规划算法
引用本文:陆惠民.项目附加资源优化的整数规划算法[J].系统工程理论与实践,1999,19(8):80-85.
作者姓名:陆惠民
作者单位:东南大学土木工程学院
摘    要:根据网络计划技术中的关键线路法CPM的时间参数分析,提出了一个工程项目建设过程中附加资源的混合整数规划模型,使建设项目在充分利用自身已有资源的前提下得到附加租赁机械设备和附加资源的使用安排计划,并使所支付的费用最低

关 键 词:附加资源  混合整数规划  关键线路法  寻优    
修稿时间::1998-08-1

An Integer Programme Algorithm for Additional Resource Optimization
LU Huimin.An Integer Programme Algorithm for Additional Resource Optimization[J].Systems Engineering —Theory & Practice,1999,19(8):80-85.
Authors:LU Huimin
Institution:Institute of Civil Engineering; Southeast University
Abstract:According to the time parameter analysis of critical path method (CPM), a mix integer programme model of additional resources in project construction has been presented. On the basis of the model, we can not only obtain a schedule of using additional leased equipment and additional resources but also gain the lowest disbursement under the fully utilization of ready made resources.
Keywords:additional resources  mix integer programme  critical path method (CPM)  optimization  