浅埋软岩隧道大变形特征及控制措施
引用本文:李建敦,肖靖,江鸿,杨林,陈世豪.浅埋软岩隧道大变形特征及控制措施[J].科学技术与工程,2022,22(3):1243-1249.
作者姓名:李建敦  肖靖  江鸿  杨林  陈世豪
作者单位:中交第二航务工程局有限公司
基金项目:云南省交通运输厅科技创新示范项目(云交科教[2019]15号)
摘    要:为了解决浅埋软岩隧道在开挖过程中发生大变形的问题,依托在建隧道工程,分析隧道初支变形及破坏特征,并利用数值模拟软件对大变形原因进行分析,提出合理的变形控制措施.结果表明:洞口浅埋段围岩受到开挖扰动和地下水影响,围岩变形量大,纵向变形分布不规律;开挖初期变形快且变形速率大,最高达到38.4 mm/d;变形持续时间长,变形...

关 键 词:浅埋隧道工程  软岩  大变形特征  数值模拟  控制措施
收稿时间:2021/4/22 0:00:00
修稿时间:2022/1/7 0:00:00

Study on Large Deformation Characteristics and Control Measures of Shallow Buried Soft Rock Tunnel
Li Jiandun,Xiao Jing,Jiang Hong,Yang Lin,Chen Shihao.Study on Large Deformation Characteristics and Control Measures of Shallow Buried Soft Rock Tunnel[J].Science Technology and Engineering,2022,22(3):1243-1249.
Authors:Li Jiandun  Xiao Jing  Jiang Hong  Yang Lin  Chen Shihao
Institution:CCCC Second Harbor Engineering Co., Ltd
Abstract:In order to solve the problem of large deformation of shallow soft rock tunnel during excavation, this paper relies on the tunnel project under construction, analyzes the deformation and failure characteristics of the initial support of the tunnel, and uses numerical simulation software to analyze the cause of the large deformation and propose a reasonable deformation control measures. The results show that the surrounding rock at the shallow buried section of the cave entrance is affected by excavation disturbances and groundwater. The surrounding rock has a large amount of deformation and the longitudinal deformation is irregularly distributed; the initial deformation of the excavation is fast and the deformation rate is large, up to 38.4mm/d; the deformation lasts for a long time , The deformation can reach 10.2mm/d in the later stage of deformation; the deformation mainly occurs in the upper and middle step excavation stage, about 70%; the initial support stress is too large, and the excessive development of the plastic zone is the main reason for the large deformation of the tunnel. According to on-site monitoring data and numerical simulation results, comprehensive treatment measures are proposed to optimize construction methods, improve support parameters, carry out precipitation in the cave, and increase the amount of reserved deformation. The research results can provide references for the prevention and treatment of large deformations similar to soft rock tunnels.
Keywords:shallow-buried tunnel engineering  soft rock  large deformation characteristics  numerical simulation  control measures
点击此处可从《科学技术与工程》浏览原始摘要信息
点击此处可从《科学技术与工程》下载免费的PDF全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号