混凝土坝浇筑机械联合施工的模拟优化及其应用
引用本文:周厚贵,戴志清,张开广,孙昌忠,曹生荣.混凝土坝浇筑机械联合施工的模拟优化及其应用[J].三峡大学学报(自然科学版),2014(2):6-10.
作者姓名:周厚贵  戴志清  张开广  孙昌忠  曹生荣
作者单位:中国能源建设集团有限公司;中国葛洲坝集团股份有限公司;武汉大学水资源与水电工程科学国家重点实验室;
基金项目:中央高校基本科研业务费专项资金资助项目(5082022);湖北省自然科学基金项目(2009CDZ038)
摘    要:在混凝土坝的施工过程中,普遍存在入仓机械联合浇筑一个混凝土仓位的情况.以南水北调中线丹江口大坝加高工程为背景,通过对入仓机械联合施工的目的、要求和限制条件的分析,建立了混凝土坝入仓机械联合施工的模拟与优化模型.模拟与优化模型以提高入仓机械利用率、加快施工进度为目标,通过对入仓机械的优化调度,产生与实际施工过程极为接近的、理想的浇筑方案.通过模拟与优化模型在丹江口大坝加高工程中的应用表明,模拟计算结果符合工程施工实际,制定的浇筑方案在实际施工中切实可行,对于混凝土坝施工的指导及其实际应用具有理论意义和工程实用价值,且在混凝土坝施工中具有普遍意义和推广价值.

关 键 词:施工模拟  施工优化  混凝土坝  联合施工  丹江口大坝加高工程

Simulation and Optimization Model for Joint Construction of Pouring Machines in Concrete Dam and Its Application
Zhou Hougui,Dai Zhiqing,Zhang Kaiguang,Sun Changzhong,Cao Shengrong.Simulation and Optimization Model for Joint Construction of Pouring Machines in Concrete Dam and Its Application[J].Journal of China Three Gorges University(Natural Sciences),2014(2):6-10.
Authors:Zhou Hougui  Dai Zhiqing  Zhang Kaiguang  Sun Changzhong  Cao Shengrong
Institution:1. China Energy Engineering Group Co. , Ltd. ,Beijing 100029, China; 2. China Gezhouba Group Co. , Ltd. , Yichang 443002, China; 3. State Key Laboratory of Water Resources and Hydropower Engineering Science, Wuhan Univ. , Wuhan 430072, China)
Abstract:There are always situations that the pouring machines pour the same bin jointly in concrete dam construction. Based on Danjiangkou dam heightening project of middle route of South-to-North Water Transfer Project, by systems analysis of objectives, requirements and limiting conditions of joint construction of pouring machines, a simulation and optimization model for joint construction of pouring machines in concrete dam is established. The model aims at improving pouring machine efficiency and speeding up construction progress, producing a satisfactory construction scheme extremely similar to real construction process by optimal operation of pouring machines. Application of the proposed model to Danjiangkou dam heightening project shows that the simulation results accord with project practice; and the pouring scheme can be used in real construction. The model has universal significance and popularization value in concrete dam construction; and it has great functions in concrete dam construction in theory and project practice.
Keywords:construction simulation  construction optimization  concrete dam  joint construction  Danjiangkou dam heightening project