组合梁斜拉桥施工仿真分析
引用本文:林致胜.组合梁斜拉桥施工仿真分析[J].南京邮电大学学报(自然科学版),2009,9(21).
作者姓名:林致胜
作者单位:广州市华南理工大学土木与交通学院
摘    要:组合梁斜拉桥作为一种高次超静定结构,其施工过程中的各项参数变化都会对成桥线形与应力造成影响,通过计算机仿真分析准确模拟其施工过程,并对计算结果进行分析,可作为施工控制中决策的依据与参考。

关 键 词:组合梁斜拉桥  仿真分析  施工控制
收稿时间:6/19/2009 6:21:51 PM
修稿时间:8/15/2009 5:54:40 PM

Construction Simulation of Composite-girder Cable-Stayed Bridge
Lin Zhisheng.Construction Simulation of Composite-girder Cable-Stayed Bridge[J].Journal of Nanjing University of Posts and Telecommunications,2009,9(21).
Authors:Lin Zhisheng
Abstract:The linear and stress of composite-girder cable-stayed bridge will be included by the changes of some parameters during construction as a high hyperstatic structure. Simulating accurately the construction process with computer and make a analysis of the results can be the basis and reference for decision-making during construction control.
Keywords:Composite-girder Cable-Stayed Bridge Simulation analysis Construction control