首页 | 本学科首页   官方微博 | 高级检索  
     检索      

Heuristic algorithm for RCPSP with the objective of minimizing activities' cost
作者姓名:Liu Zhenyuan & Wang Hongwei Inst. of Systems Engineering  Huazhong Univ. of Science and Technology  Wuhan  P. R. China
作者单位:Liu Zhenyuan & Wang Hongwei Inst. of Systems Engineering,Huazhong Univ. of Science and Technology,Wuhan 430074,P. R. China
摘    要:1.INTRODUCTIONPartner selection is an i mportant problemin supplychain management.When we design a constructionsupply chainin which general contractor is the kernelentity,general contractor’s project scheduling will beconstrained by the capacities of the renewable re-sources supplied by the partners such as subcontrac-tor,ready-mix concrete vendor.We should considerhowto get theleast activities’cost of the project withthe constraints of due date and resource capacities ofevery partner re…

收稿时间:9 December 2004

Heuristic algorithm for RCPSP with the objective of minimizing activities' cost
Liu Zhenyuan & Wang Hongwei Inst. of Systems Engineering,Huazhong Univ. of Science and Technology,Wuhan ,P. R. China.Heuristic algorithm for RCPSP with the objective of minimizing activities'''' cost[J].Journal of Systems Engineering and Electronics,2006,17(1):96-102.
Authors:Liu Zhenyuan  Wang Hongwei
Institution:Inst. of Systems Engineering, Huazhong Univ. of Science and Technology, Wuhan 430074, P. R. China
Abstract:Resource-constrained project scheduling problem(RCPSP) is an important problem in research on project management. But there has been little attention paid to the objective of minimizing activities' cost with the resource constraints that is a critical sub-problem in partner selection of construction supply chain management because the capacities of the renewable resources supplied by the partners will effect on the project scheduling. Its mathematic model is presented firstly, and analysis on the characteristic of the problem shows that the objective function is non-regular and the problem is NP-complete following which the basic idea for solution is clarified. Based on a definition of preposing activity cost matrix, a heuristic algorithm is brought forward. Analyses on the complexity of the heuristics and the result of numerical studies show that the heuristic algorithm is feasible and relatively effective.
Keywords:systems engineering  resource-constrained project scheduling problem  activities' cost  preposing activity cost matrix  heuristic algorithm
本文献已被 CNKI 万方数据 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号