三峡工程坝址区主要工程地质问题研究
引用本文:薛果夫,陈又华. 三峡工程坝址区主要工程地质问题研究[J]. 中国工程科学, 2011, 9(7): 51-60
作者姓名:薛果夫  陈又华
作者单位:长江水利委员会长江勘测规划设计研究院,武汉430010;长江水利委员会长江勘测规划设计研究院,武汉430010
摘    要:简要介绍了工程坝址区最为关键的坝基深层抗滑稳定、永久船闸高坡稳定、地下电站主厂房围岩块体稳定、断裂构造等几个工程地质问题研究过程、方法、工作内容及基本结论,并结合工程施工、监测及运行有关情况对各专题进行全面总结与评价。

关 键 词:三峡坝区  工程地质问题  勘察研究  总结

The research on main engineering geological problems in dam-site of Three Gorges Project
Xue Guofu and Chen Youhua. The research on main engineering geological problems in dam-site of Three Gorges Project[J]. Engineering Sciences, 2011, 9(7): 51-60
Authors:Xue Guofu and Chen Youhua
Abstract:The site geological investigation and research work of the Three Gorges Project (TGP) has lasted for more than 50 years, which catches wide attention at home and abroad due to its depth and extent. The research processes, approaches, contents and basic conclusions for the key engineering geological problems of dam site are briefly introduced, including the deep anti-sliding stability of dam foundation, the high slope stability of permanent ship-lock, the surrounding rock mass stability of the main plant of underground powerhouse and the faulted structures. Finally, an overall summarization and evaluation of the research are presented based on the situations of project construction, monitoring and operation.
Keywords:dam area of TGP   engineering geological problems   investigation and research   summarization